Freight lift without pit over 3 floors
For this project, a well-known architect approached us with a special challenge. His customer, a large electronic components supplier, wants to connect its three floors with a freight elevator. Sounds like a simple task.
The challenge was that the first breakthrough had already been made and that in the lowest stop – in the basement – only a pit with a maximum depth of 130mm could be made. Due to this requirement, a solution with a lifting table or classic freight elevator would not have been possible. In addition, it was a must that 2 pallets had to be transported at the same time, which seemed hardly feasible due to the already existing – almost too narrow – breakthrough.
We have adapted our hydraulic column lifter exactly to the existing breakthrough. We positioned parts of the shaft scaffolding outside the shaft to gain platform width. Thanks to a special design, we were also able to adjust the construction height in such a way that the existing pit depth was sufficient. Here we were able to help customers save high costs for structural measures.
Details of the freight lift without pit
Delivery from the column lifter
Lowest stop of the hydraulic freight lift
At the lower stop, in the basement, a 130 mm deep concrete pit was made so that there is no step when loading the platform. The platform of the column lifter sinks into this pit and closes flush with the floor.
On three sides, the lifting area of the freight lift is secured by a fixed lattice or sheet metal shaft. On one side there is a double door, which is secured by a forced contact.
The door of the column lifter in the basement can only be opened if the platform is also properly in this position.
At the back of the picture you can see the oil tank and the control of the system. We usually install these in the lowest stop, as this requires the least hose and cable lengths.
In addition, you also save laying in cable ducts and get a nicer look.
Middle stop from the column lifter without pit
Our continuous shaft scaffolding also secures in the second stop – on the middle floor – on three sides as fall protection. It also prevents encroachment in the danger zone. The mesh size of the shaft is produced according to the applicable standard.
In this stop, a door is also installed with a forced contact. However, this is located on the opposite side. The freight lift without pit is therefore a through-loader.
The gap between our shaft scaffolding and the floor is closed by the customer with a connection plate. This prevents anything from falling down.
Top stop of the freight lift with shaft scaffolding
Order lifting tables now
If you have any questions, please contact us immediately. We are looking forward to it!