2 pieces • 10,000 kg load capacity • 9 x 5 meter platform • 2 meter lifting height

Lifting table in cable car valley station

Lifting table for loading and unloading a cable car ✓ galvanized design ✓ Use in the cable car valley station ✓ With assembly

XXL version
2 scissor lift tables, each with a load capacity of 10,000 kg.
Logistics & Assembly
Connected on site – aligned and screwed together with millimeter precision.
Synchronous Hub
Hydraulic multiple flow divider for even lifting.
XXL lifting table in the valley station
Hydraulic scissor lift with view of the rock face in the background.

The incredibly exciting Schlithornbahn 20XX project – the lifting platform for the cable car – is nearing completion after almost two years. Many personal and virtual meetings, countless phone calls, and innumerable hours of planning and installation later, we can be proud of having achieved such a remarkable feat.

An impressive project is underway at the Schilthorn in the canton of Bern, Switzerland: The construction of new cable cars promises not only comfort for passengers but also impresses with a logistical masterpiece in the transport of goods. A unique system for freight transport has been developed on the route between Stechelberg, the valley station, and Mürren, the mountain station.

A shuttle train for 85 people ensures that not only visitors, but also a wide variety of materials and general cargo reach their destination safely and efficiently – thanks to a clever underload transport system.

Nothing is left to chance. Normal general cargo is transported in specially manufactured containers that are hung under the cabins fully automatically by a precise crane system. This smooth automation not only speeds up the process, but also minimizes the risk of errors, so that the goods can overcome the steep heights quickly and safely.

valley station special load

lifting table for special loads

Things get interesting, however, with oversized special loads – these can't simply be attached automatically. This is where the technical expertise of the project managers comes into play: Using massive lifting platforms installed beneath the cabins, the heavy load is lifted and positioned. The lifting platforms are first lowered to ground level to allow the load to be maneuvered underneath. Once everything is in place, the exciting moment of lifting begins.

The special load is carefully lifted under the cabin centimeter by centimeter before being precisely attached to it.

Only when the lifting table is completely lowered again can the cabin begin its journey with the special load - a feat of strength that requires precision and coordination. Once the destination is reached, the procedure is reversed: the lifting table slowly raises the load again and the cabin is relieved. This creates a seamless and fascinating process that combines technology and logistics and makes the new cable car construction on the Schilthorn a true masterpiece.

Details of the lifting table for loading a cable car

XXL lifting table in the valley station

planning and tender basis of the project

The start of the project was identical to all other previous lifting table projects. The customer sent us his specifications with the rough requirements.

2 scissor lifts, each with a load capacity of 10,000 kg and a platform size of 9 x 5 meters. The effective lift was specified as 2 meters. There were also a few special components.

After initial telephone calls, we decided to offer, develop and implement this project.

Part number 4 is introduced

XXL scissor lift table consists of 4 smaller lifting tables

Due to the very large platform, it was not possible to deliver the hydraulic scissor lift table in one piece. For this reason, we decided to build 4 smaller lift tables and then connect them on site.

In the picture, 3 of these lifting tables have already been installed in the excavation pit. The fourth and final part is lifted into position by the construction crane with centimeter precision. Once there, our technicians aligned the lifting table precisely and screwed it to the remaining components.

We left out the middle platform covers for the test run so that all components of the XXL lifting table can be easily accessed for any repairs.

Lifting table complete

Commissioning, training and handover

After the test runs, the last platform covers were installed and commissioning was carried out.

We then provided comprehensive training to the client – the cable car manufacturer – and the future operator. Not only was the functionality explained, but also the mechanics, hydraulics, and control systems.

View under the platform of the XXL lifting table

Four scissors lift the platform synchronously upwards

Four scissor packs with their own cylinders were installed under the lifting table. The four platforms are bolted together, but would not lift at exactly the same time if the load was unevenly distributed.

For this reason, we have installed a hydraulic multiple flow divider. This ensures even lifting even when the individual platforms are subjected to unequal loads.